Airport Central railway station (officially Airport Central Station) is a station for underground commuter rail services at terminals T1 and T2 of Perth Airport in Western Australia. The station is one of three new stations that were built as part of the Forrestfield–Airport Link project, and is served by Airport line services.
Underground station in Perth, Western Australia
Airport Central
Airport Central Station viewed from concourse
General information
Location
Horrie Miller Drive, Perth Airport Western Australia Australia
Airport Central is located adjacent to the air traffic control tower at Perth Airport terminals T1 and T2.
The contract for the Forrestfield–Airport Link, which consists of 8 kilometres (5.0mi) of twin bored tunnels and three new stations, was awarded to Salini Impregilo and NRW Pty Ltd in April 2016. Construction on Airport Central Station began in March 2017 following preparatory works. By January 2018, excavation was complete, and in May 2018, the two tunnel boring machines (TBMs) reached the station after tunnelling from High Wycombe. The TBMs left the station tunnelling north-west the following month, and construction of the rest of the station started after that. In addition to the station, a 280-metre (920ft) elevated walkway was built by Georgiou Group, linking the station to the airport's terminal T1.
Originally planned to open in 2020, the line officially opened on 9 October 2022.[1] It is served by trains every 12 minutes during peak hour, and every 15 minutes outside peak hour and on weekends and public holidays. At night, trains are half-hourly or hourly. The journey to Perth station normally takes 18 minutes.
Description
Public art along the northern interior wall of the station. The longest escalator in the southern hemisphere can be seen as well.Station platform with a Transperth B-series train on the left
Airport Central Station is located adjacent to the air traffic control tower at Perth Airport terminals T1 and T2. To the east, the adjacent station is High Wycombe station. To the north-west, the adjacent station is Redcliffe station, which leads to Perth station and connections to all the other lines on the Transperth system.[2]
The station has three levels: a below-ground platform level, a below-ground concourse level above the platform level, and an above-ground entrance level which connects to a 280-metre-long (920ft) elevated walkway called the Skybridge. The Skybridge crosses over a car park towards T1, with lifts and stairs connecting the Skybridge to external ground level approximately 200 metres (660ft) east of T2. Linking the entrance level to the concourse level are two lifts and three escalators,[3] which are the longest operational escalators in the southern hemisphere at 35 metres (115ft) long and 15 metres (49ft) high;[4][5][6] although they will be overtaken by 45-metre (148ft) escalators at Sydney Central station in 2024.[7] On the concourse are fare gates, toilets, and a staff office. Linking the concourse to the platform are two lifts, two pairs of escalators, and two sets of stairs. There are also two emergency staircases at either end of the platform, and two emergency staircases from the concourse, which all lead to external ground level.[3] The platform level consists of an island platform 12.5 metres (41ft) wide and 150 metres (490ft) long, each of the two platform faces accommodating a six-car Transperth train.[8]
Public art
The design of the roof is based on the contours of aircraft. An artwork designed by Anne Neil and John Walley to evoke birds and flight is suspended from the ceiling. On the southern wall is a large glass feature consisting of 50 panels with an artwork designed to "describe the Noongar connection to the river and estuary waters, and the journeys traditionally taken in accordance with the six[lower-alpha 1] seasons."[8][12][13]
History
During initial planning, the station was called Consolidated Airport station.[14] The station was renamed to its present name in April 2016 upon the awarding of the main contract. For the most part, the Forrestfield–Airport Link project came under one contract, worth $1.176 billion and awarded to Salini Impregilo and NRW Pty Ltd. This included the construction of tunnels from High Wycombe to Bayswater, and three stations: Forrestfield (later renamed High Wycombe), Airport Central, and Belmont (later renamed Redcliffe) stations.[15][16] The construction of the Skybridge was under a different contract, awarded to Georgiou Group in late-2018. The Skybridge was funded as part of the Forrestfield–Airport Link project, but the construction was managed by Perth Airport.[17][18] At the time, the station was expected to be in operation by 2020.[15][16]
In late 2016, work began on reorganising the airport's car park and car rental booths to make way for the Airport Central station construction site. The station box was planned to be constructed between March 2017 and February 2018.[19] During this, several archaeological discoveries were made, including a headstone from the 1890s.[20][21] Construction on Airport Central station began in May 2017,[22] starting with the construction of diaphragm walls.[20] The station's design was released on 28 May 2017.[23] The diaphragm walls were completed in July 2017,[24] allowing excavation to begin the following month.[25] Excavation was completed in January 2018 and construction of the concrete base slab commenced the following month.[26] The base slab was completed by April 2018.[27]
The two tunnel boring machines (TBMs) were planned to arrive at Airport Central station in late-February and late-March 2018 respectively, having tunnelled from High Wycombe.[24] This was delayed after the first TBM, Grace, was stopped on 14 February following a ground disturbance issue.[28] This also caused the second TBM, Sandy, to stop on 28 March.[29] The two TBMs restarted in April.[30] TBM Grace arrived at the station on 8 May 2018,[31][32] and TBM Sandy arrived later that month.[31][33] After undergoing maintenance, both TBMs left the station in July, tunnelling towards Redcliffe. Construction on other elements of the station commenced after that,[34] including staircases and infrastructure for the escalators and lifts.[35]
Airport Central station under construction in May 2020
In November 2018, construction on the Skybridge started.[36] Construction on Airport Central station's steel structure and the concrete concourse slab began in early-2019.[37] The 35-metre-long (115ft) escalators were installed in May and June 2019.[38][39] In mid-2019, construction of the platform and ventilation structures at the eastern and western ends of the station began,[40] and the modules for the Skybridge began to be lifted into place.[41][42] By November 2019, the concourse slab and the steel lift frames were complete,[43] and the Skybridge was connected to the station.[44] The Skybridge achieved practical completion in early-2020.[45] By March 2020, the station was 70% complete and the roof was beginning to be installed.[46][47] The roof was mostly complete by June 2020, allowing work such as the fit-out of escalators and lifts,[48][49] and the installation of cladding along the walls to commence.[50][51]
On 18 December 2018, Transport Minister Rita Saffioti announced the opening date of the project had been delayed from 2020 to 2021.[52] In May 2021, Saffioti announced that the project had been delayed again, this time with the opening date being in the first half of 2022.[53][54] Following the state budget on 12 May 2022, the government changed its position on the line's opening date, saying the line will open some time later in the year.[55][56] On 16 August, the opening date was revealed to be 9 October 2022,[57][58] which is when the station did open officially.[1]
Services
Airport Central station is served by the Airport line on the Transperth network.[2] These services are operated by Transperth Train Operations, a division of the PTA.[59][60] To the east, the line terminates at the next station, High Wycombe. To the west, the line joins the Midland line two stations along at Bayswater, running alongside that line to Perth station, before running alongside the Fremantle line, terminating at Claremont station.[2] Airport line trains stop at the station every 12 minutes during peak hour on weekdays and every 15 minutes outside peak hour and on weekends and public holidays. At night, trains are half-hourly or hourly.[61] The station is predicted to have average daily boardings of 6,100,[8] rising to 11,000 in 2031.[14][62] The journey to Perth station takes 18 minutes.[8][61] The station is in fare zone two, and there is no surcharge.[8][62] South-west of the station is a bus stop which is used by rail replacement bus services to Perth and High Wycombe.[3]
The Noongar peoples recognise six seasons whose time frame is defined by specific observable changes to the environment rather than calendar dates.[9] These seasons are:[10][11]
first summer (Birak or Biroc),
second summer (Bunuru or Bunuroo),
autumn (Djeran or Wanyarang),
winter (Makuru or Muguroo),
first spring (Djilba), and
second spring (Kambarang).
References
McGowan, Mark; Saffioti, Rita (9 October 2022). "All aboard as new METRONET Airport Line opens". Media Statements of the Government of Western Australia (Media statement). Western Australia: Government of Western Australia. Retrieved 9 October 2022. The METRONET Airport Line is officially open with the very first train pulling out of High Wycombe Station this morning.
"Train System Map"(PDF). Transperth. Archived(PDF) from the original on 16 August 2022. Retrieved 31 August 2022.
"Airport Central Map"(PDF). Transperth. Archived(PDF) from the original on 16 August 2022. Retrieved 31 August 2022.
Barrow, Jason (2016). "Indigenous Weather Knowledge – Nyoongar calendar". Bureau of Meteorology. Commonwealth of Australia. Retrieved 12 October 2022. The Nyoongar seasonal calendar includes six different seasons in a yearly cycle. These are Birak, Bunuru, Djeran, Makuru, Djilba and Kambarang.
"Art and Cultural Guide"(PDF). Fiona Stanley Hospital. Fiona Stanley Fremantle Hospitals Group, South Metropolitan Health Service, Government of Western Australia. 2020. Retrieved 12 October 2022. The six Noongar seasons of Djilba (July, August), Kambarang (September, October), Biroc (November, December), Bunuroo (January, February), Wanyarang (March, April) and Muguroo (May, June).
Другой контент может иметь иную лицензию. Перед использованием материалов сайта WikiSort.org внимательно изучите правила лицензирования конкретных элементов наполнения сайта.
2019-2025 WikiSort.org - проект по пересортировке и дополнению контента Википедии